RENCANA ANGGARAN BIAYA REHAB TEMPAT IBADAH UK. 12 M X 12 M | ||||||
YAYASAN PENDIDIKAN ISLAN RIYADLUS SHOLIHIN | ||||||
DESA NEGARA TULANG BAWANG KEC. BUNGA MAYANG LAMPUNG UTARA | ||||||
NO | URAIAN PEKERJAAN | VOLUME | HARGA SATUAN (Rp) | JUMLAH | ||
I | Perbaiakn Plapound Triplek & Lisplank | | | | | |
| rangka plapound triplek | 156,6 | M² | 58,500 | Rp | 9,161,100 |
| Ruang kelas : uk. 12 m x 12 m x 90% | 129,6 | m² | 57,000 | Rp | 7,387,200 |
| Serambi : 2,5 m x 12 m x 90% | 27 | m² | 57,000 | Rp | 1,539,000 |
| Lisplang | | Is | | Rp | 1,446,600 |
| | | | | | 19,533,900 |
| | | | | | |
II | Pemasangan lantai keramik | | | | | |
| Ruang kelas : uk. 12 m x 12 m | 144 | m² | 58,000 | Rp | 8,352,000 |
| Serambi : 2,5 x 12 | 30 | m² | 58,000 | Rp | 1,740,000 |
| | | | | | 10,092,000 |
| | | | | | |
III | Pengecatan dinding dan Plapound | | | | | |
| Plapound | 144 | m² | 16,645 | Rp | 2,396,880 |
| Dinding luar dalam : (48 m x 3,5) x 2 | 336 | m² | 16,645 | Rp | 5,592,720 |
| Pengecatan kuzen-kuzen | | Is | | Rp | 1,850,000 |
| | | | | | 9,839,600 |
| | | | | | |
IV | Perbaikan pintu dan jendela | | | | | |
| Daun pintu | 1 | bh | 675,000 | Rp | 675,000 |
| Daun jendela | 9 | bh | 150,000 | Rp | 1,350,000 |
| Engsel-engsel | | Is | | Rp | 750,000 |
| Kunci royal B | 1 | bh | | Rp | 100,000 |
| | | | | | 2,875,000 |
| | | | | | |
V | Perbaikan rangka/ kuda-kuda | | | | | |
| Per. Kuda-kuda kayu kls II: uk. 8/12 | 1,80 | M² | 1,646,000 | Rp | 2,962,000 |
| Gording kayu kls. II : uk. 8/12 | 1,60 | M² | 1,646,000 | Rp | 2,633,600 |
| Kuzen-kuzen pintu & jendela kayu kls. II | 1,20 | M² | 1,719,250 | Rp | 2,063,100 |
| | | | | | 7,659,500 |
| | | | | | |
Jumlah Biaya Rehab | | | ||||
Rp | 50,000,000 |
ANGGARAN RENCANA PEMBANGUNAN REHAP TEMPAT IBADAH YAYASAN PENDIDIKAN ISLAM RIYADLUS SHOLIHIN DISIAPKAN OLEH : PANITIA PEMBANGUNAN REHAP TEMPAT IBADAH YAYASAN PENDIDIKAN ISLAM RIYADLUS SHOLIHIN LAMPUNG UTARA – INDONESIA |
Tidak ada komentar:
Posting Komentar